We started to frame in late December. They laid out all the walls first.
Monday, January 25, 2010
Sunday, January 24, 2010
Plenty of Steel
The steel beams were fabricated off-site and hoisted into place with a crane. It was impressive seeing all the bolt-holes line up exactly (no slotted holes either). The fabricator was Pearce Welding.
Thursday, January 21, 2010
The Foundation and Waterproofing
The foundation is done. For waterproofing we used a system called Tuff-N-Dri.
Forming the Foundation
We decided to go with a poured concrete foundation. The photos below show the sequence of setting up the forms.
Monday, January 18, 2010
Pinning the Foundation
We had the site engineer pin (spike with pink tape) the corners of the foundations. This way we the house will be located in the right location (or at least know who to blame if it is not).
Temporary Electric Service
We brought in temporary electrical service. The electrician did a really nice job. He even painted the mounting board grey for a neat appearance.